Concrete Floor Slab-On-Ground Has Settled In A Finished Area

Article Number

1.5

Condition

CONCRETE FLOOR SLAB-ON-GROUND HAS SETTLED IN A FINISHED AREA

Acceptable Performance/Condition

At the perimeter of rooms, concrete floor slabs shall not settle more than 12 mm from their original position.

Warranty

One-Year - Work and Materials

Action

Slabs that settle more than the acceptable condition shall be repaired.

Remarks

None

  